- Home
- Departments
- Administrator
- Road Projects
Road Projects
______________________________________________________________________________
The Village of Little Chute Department of Public Works is constantly undertaking a variety of projects ranging form road construction, water and sewer replacement and storm water management. Throughout the course of the year, road project updates will be available.
2019 UTILITY & STREET CONSTUCTION – EVERGREEN DRIVE
Schedule: June 2019 to October 2019
Project Description:
Updated Weekly Schedule (November 4th to November 8th)
EVERGREEN DRIVE UTILITIES
Don Hietpas & Sons has completed the storm sewer utility work on Evergreen Drive between French Road & Holland Road.
EVERGREEN DRIVE PAVING
Vinton Construction is the general contractor for the Village paving contract on Evergreen Drive. Vinton has completed all of the concrete paving from French Road to Holland Road. N.E. Asphalt has completed the asphalt driveways and asphalt transitions for the intersections. Vinton’s grading crews continue performing site grading in preparation for the landscape restoration. Highway Landscape will be on-site restoring, seeding, and mulching disturbed areas. Evergreen Drive remains an active construction site. For your safety as well as those working in the area, please avoid use when possible.
Traffic Impacts: Evergreen Drive has been re-opened to two-way traffic between French Road and Holland Road. Evergreen Drive is posted for “Local Traffic Only” and remains closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed pavement.
2019 ASPHALT PAVING PROJECTS - PARK AVENUE ASPHALT PAVING
Project Description:
The proposed project consists of asphalt paving approximately 7,200 square yards. The utilities under the pavement are in good condition and will not require replacement. This project will include the removal of the existing asphalt and gravel base. The subgrade will be reshaped and compacted. Finally, a new gravel base and asphalt pavement will be installed. Additional work will include rim adjustment of structures and replacement of damaged curb and gutter in spot locations.
Park Avenue is now open to through traffic with no construction restrictions. Project is complete.
_______________________________________________________________________________
Project Update Monday, June 10th
Project Walk-Thru Dates Have Been Set
West Evergreen Drive – Wednesday, June 12th
For more information click here.
Park Avenue – Wednesday, June 26th
For more information click here.
Bid Documents
To bid on the 2019 utility and street reconstruction projects click the link here and enter the following quest numbers:
Park Avenue Asphalt Paving (2019001)
Quest E-Bid Doc # 6255729
Evergreen Drive Storm Sewer (2019002)
Quest E-Bid Doc # 6255906
Evergreen Drive Concrete Paving (2019003)
Quest E-Bid Doc # 6255921
The utility (storm Sewer) and concrete street reconstruction is necessary on West Evergreen Drive to accommodate new development and increased traffic load. The proposed work includes new concrete pavement with integral curb and gutter, storm sewer, and grass restoration areas. The new pavement on West Evergreen Drive will be comprised of two 12-foot-wide drive lanes and one 14-foot-wide common center turning lane.
Park Avenue
Asphalt pavement replacement is needed on Park Avenue because it has reached the useful life expectancy of the pavement. Because the utilities are in relatively good condition with curb and gutter requiring only spot repairs it is best to replace the asphalt pavement and not install a 50-year concrete pavement over the ageing infrastructure. With asphalt being approximately half the cost of concrete at approximately half the life cycle, it is economically more feasible to provide a pavement that will last 20 to 25 years to better match with the utilities life cycle before a total reconstruction is necessary. The existing condition of the asphalt pavement has reached a level where maintenance continues to increase without extending the pavement life. A pavement overlay is not an option due to the current condition of the pavement and subbase. To prevent further surface water intrusion and to correct sub-base rutting the pavement will be removed and subbase regraded and compacted prior to placement of granular base material and new asphalt pavement.
Public Informational Meeting – 4/3/19
Click here for meeting outline.
Public Hearing - 4/17/19
Click here for Frequently Asked Questions.
Click here for power point presentation.
WIS 441 Bridge Painting
Project Location: WIS 441 over Fox River, WIS 96, and Railroad Outagamie County
WISDOT will be conducting a maintenance painting project on the WIS 441 bridge over the Fox River, WIS 96, and Canadian National Railroad. Anticipated work will begin in April 2018. Work will continue until November 2018 and finish any remaining work in April of 2019.
WIS 441 will remain open to at least one lane of traffic in each direction at all times during the project. The single lane closures will be limited to nighttime only from 8:00 pm to 6:00 am.
Thank you for your patience throughout the reconstruction process!
Contact Us:
-
Laura Braatz
Public Works Administrative Assistant
(920) 423-3865
Email Public WorksVillage of Little Chute
108 W. Main Street
Little Chute, WI 54140